LAB115218CS-003-optimized

TYPE APPROVAL CERTIFICATE
No. LAB115218CS/003

This is to certify that the product identified below is in compliance with the
regulations herewith specified.

Description Devices for the passage of pipes through A or B
Class divisions
Type Roxtec SLEEV-IT WT MAR ALU on aluminium decks
Applicant ROXTEC INTERNATIONAL AB
ROMBVAGEN 2, P.O. BOX 540
SE-37123 KARLSKRONA

SWEDEN

Manufacturer ROXTEC INTERNATIONAL AB
Place of manufacture ROMBVAGEN 2, P.O. BOX 540
SE-37123 KARLSKRONA

SWEDEN

Reference standardsIMO Res. MSC.307(88)-(2010 FTP Code)

Issued in Genoa on May 10, 2018. This Certificate is valid until May 9, 2023

RINA Services S.p.A.

Enrico Cabella

This certificate consists of this page and 1 enclosure

RINA Services S.p.A.

Via Corsica, 12 - 16128 Genova - Italia

Tel. +39 010 53851

Fax. +39 010 5351000

TYPE APPROVAL CERTIFICATE
No. LAB115218CS/003
Enclosure - Page 1 of 1
Roxtec SLEEV-IT WT MAR ALU on aluminium decks

Product description

Device for the passage of plastic pipes (not reinforced and multilayer) through A Class
aluminium decks composed of a stainless steel tubular casing fitted with aluminium flange
welded to the deck plate. Decks insulated on the side exposed to the fire by means of two
layers of mineral wool 30 mm thick each and having density of 130 kg/m3. The deck

insulation covers also the transits.

Field of application

Fire resistant A-60 Class plastic pipe penetrations through aluminium decks as per following

tables:

TYPE OF TRANSITS - PIPE DIAMETER ADDITIONAL TRANSIT FIXING
INSULATION AND NOTES
Transits from SLEEV-IT WT-MAR16M ALU up No additional Seal fitted on the
to SLEEV-IT WT-MAR225M ALU insulation exposed side.
pipe diameter from 16 mm up to 225 mm

Reference documents

Roxtec drawings included in DBI Report No. PGA10802A dated 29 August 2016 and in CTO

Report No. RS-17/B-210/E dated 2 June 2017.

Tests carried out

Tests as per DBI Report No. PGA10802A dated 29 August 2016 and CTO Report No. RS-
17/B-210/E dated 2 June 2017 issued according to IMO 2010 FTP Code - Annex 1 - Part 3.
Note: Transits SLEEV-IT WT-MAR16M and SLEEV-IT WT-MAR225M were subjected to
hydrostatic test (water - 1.5 bar) for 60 minutes and gas-tightness test (helium - 1 bar) for 30
minutes without any leakage - Tests as per DNV-GL Survey Report No. N141EX90 dated 30

June 2017.

General conditions for the approval
a) The initial conditions verified by RINA at the time of the approval are to be maintained

b) Any changes to the initial conditions are to be promptly communicated to RINA, which reserves the right to

repeat the relevant assessment

c) This certificate will no be valid if the manufacturer makes any changes or modifications to the approved
equipment, which have not been notified to, and agreed with RINA

d) RINA personnel are to allowed to witness during the performances of activities, upon their request

e) The activities are to be carried out in compliance with the RINA Rules and/or other applicable Rules

f) Should the specified regulations or standards be amended during the validity of this certificate, the product is to be
reapproved prior to it being placed on board vessels to which the amended regulations or standards apply.